Hi

In a model we have several work stations needed to produce several types of products. I have a resource that can be described as a scarce equipment (a jig) meaning that only specific types of a product can be worked on in work stations where the jig is present.

For several reasons once a specific resource (jig) is used in a work station I want to keep it there for two different reasons, either;

y repetions or,
x hours.

My question is how do l lock these resources in simul8