Resource for Activity Stoppage

Resource for Activity Stoppage

Postby JBA » Fri May 09, 2014 8:12 am

I am using Activities to model Machines in a production line, and I'm using the Efficiency settings to simulate machine Stoppages.

When the machine stops, id like specify that a resource from a pool (think maintenance technician) must be allocated to fix the breakdown. If the resource isnt available, the breakdown time is extended.

I can see there is an "On Breakdown" section that can have VL added to it - is this the place to do this?

Any advice would be greatly appreciated.