Resources Button in Routing In To...Change Over Missing

Resources Button in Routing In To...Change Over Missing

Postby Felix » Mon Jun 15, 2015 8:52 am

Hi,
I'm using Simul8 2015 Professional version.
I try to us allocate resource to changeover. Read the Simul8 Resources Center on Change Overs. But, the "Resources" button seems not show anymore. Is this normal for Simul8 2015 Pro version?

I did try the "Require resource before..." as per instruction in Routing In To>Change Over tab. When I run the simulation, the resource is attached to WC when it's in working stage. It make the resource utilization same like WC.

How to assign resource for change over in simulation?

Appreciate your help.