Sequencing Activities

Sequencing Activities

Postby momar92 » Mon Mar 27, 2017 11:14 am

Hi !
I need help with a situation where sequencing is needed.

I have an activity ( say Main Activity) batching out to 4 different paths, each composed by several activities. There is only a resource and i want this resource to follow a specific sequence (ex. Start with Path A, then come to path B...)

I tried resource priority, but it appears to dont work.

Any suggestions ??

Re: Sequencing Activities

Postby jholtman » Sat Apr 15, 2017 9:00 pm

You can assign a resource at one workcenter and then release at another; I think this is the option that you want.
Jim Holtman
Data Munger Guru
jholtman (at) gmail (dot) com
What is the problem you are trying to solve?
Tell me what you want to do, not how you want to do it.


Return to “SIMUL8 Cafe”