I have a process with 3 different working items (Labels A, B and C).
All types of working items are processed in the same activity (Activity 1), but each one has a different average time of processure (A=2 minutes; B=4 minutes; C=6 minutes).
How can I parameterize Activity 1 with different work times, according the label of work type?

Thanks in advance.
Best regards!
Pedro

Re: Activity differents work times

Postby OliverPX » Tue Jun 27, 2017 2:19 pm

You can use a spreadsheet to store the data (per label, per activity), and then use this as the timing information.